Projects
Kinder Morgan Galena Park Terminal
Cima Services selected Batten Drilling to complete Kinder Morgan Galena Park terminal bus support and
bridge foundations. Job was completed in 2 weeks; ahead of schedule and no change orders issued.
Over 500 yards of grout were placed.
Kyle Field Redevelopment Project
A $485 million redevelopment project that spanned over 2 years, involving over 1,500 drilled shafts that required temporary casing, low clearance areas, and an expedited schedule that included up to six drilling rigs onsite working seven days per week.
IAH Terminal B
The foundations plan to be drilled for IAH's Terminal B by Spring 2025. Over 664 different piers have been drilled and slurried, having five drill rigs on site knocking the work out.
M.D. Anderson Cancer Center
This project was for the M.D. Anderseon Cancer Center. Working 6 days a week drilling down to depths of 110' for 381 piers, this project was completed by December 2024.
TAMU Engineering Education Complex
The specialized drill machine and crew completed 5-foot diameter belled piers by 12-foot deep with only 13’ of head clearance inside a basement. The second phase required a crawler crane with drill attachment to complete holes up to 9-foot diameter by 35-foot deep. Both phases were completed ahead of schedule.
Keppel AmFels – Parker Drilling Foundation
Designed for Parker Drilling land rig. Forty-eight 30" by 55' deep foundations completed, being formed 2' out of ground. Batten Drilling provided all shafts turnkey, supplying tied rebar, concrete, and form/finish.
Texas A&M University-RELLIS Campus Industrial Distribution Center
Contractor: Jon Tucker Construction, Ltd.
Contact: Jon 979-412-1223
(94) 18” X 40’ Auger Cast Piles
Drilled, supplied and placed grout, grout pump & placed rebar cages
Danbury Substation
Contractor: Front Line Power Construction
Contact: Jimmy 281-710-9155
(118) 18″to 84” X 15’ to 34’ Straight Shafts
Drilled and processed the 42″ & 84″ shafts by the slurry displacement method
Completed: March 2022
Traverse Wind 245k Substation
Contractor: Cajun Industries, LLC.
Contact: Alex 225-754-0275
(102) 24” to 60” X 9’ to 20’ Straight Shafts
Completed: April 2021
Shell Gas Compression Facility
Contractor: Tepsco
Contact: Jim Wheeler, 281-542-2190
(396) 12”, 16”, 18”, 24”, and 30” X 8-21’ Straight Shafts
BP Biofuels
Contractor: Pinnacle Plant Services, Inc.
Contact: Kris Miller, 409-622-1085
(6) 30” X 24’ to 37’ Straight Shafts
Processed by slurry displacement
HMSLH Bed Tower & Cath Lab
Contractor: Vaughn Construction
Contact: Todd Kast, 210-793-6059
(38) 30” X 65’ Straight Shafts
Processed by the slurry displacement method
Completed: August, 2014
Hero Stadium
Contractor: Sturdisteel
Contact: Paul Medina, 423-261-4404
(124) 18”, 24” & 30” X 20’ to 36’ – rock drilling
Completed: February, 2013
George R. Brown Convention Parking Garage
A 1,900 car parking garage located on the north side of the GRB. A constrained site, existing metro rail and downtown location were just a few obstacles encountered. Working alongside Vaughn Construction and Cemex Concrete, over 5,000 yards of grout were placed. Two auger cast drill machines and crews were mobilized to complete piles with a very demanding schedule.
FedEx Package Distribution Center
This addition to the distribution center was completed while accommodating the needs of an operational facility on a 101-acre site; construction was scheduled without disrupting ongoing operations. A crawler crane with drill attachment and Soilmec completed all temporary cased shafts ahead of schedule.
Six Flags Over Texas – SkyScreamer
A drilled pier foundation designed for the world’s tallest swing carousel ride that required seven 54-inch diameter by 70' temporary cased rock holes.