top of page

Projects List

Texas A&M University-RELLIS Campus Industrial Distribution Center

  • Contractor:  Jon Tucker Construction, Ltd.

  • Contact:  Jon 979-412-1223

  • (94) 18” X 40’ Auger Cast Piles

  • Drilled, supplied and placed grout, grout pump &  placed rebar cages

.

Kinder Morgan Galena Park Terminal

Cima Services selected Batten Drilling to complete Kinder Morgan Galena Park terminal bus support and
bridge foundations.  Job was completed in 2 weeks; ahead of schedule and no change orders issued.
Over 500 yards of grout were placed.

  • Contractor: CIMA Services, LP

  • Contact: Collin Dodd, 832-690-0990

  • Scope: (64) 18” & 24” X 40’ to 60’ Auger Cast Piles; Drilled, supplied and placed grout, placed rebar cages

  • Completed: July 2015

Shell Gas Compression Facility

  • Contractor: Tepsco

  • Contact: Jim Wheeler, 281-542-2190

  • (396) 12”, 16”, 18”, 24”, and 30” X 8-21’ Straight Shafts

.

Keppel AmFels – Parker Drilling Foundation

Designed for Parker Drilling land rig. Forty-eight 30" by 55' deep foundations completed, being formed 2' out of ground. Batten Drilling provided all shafts turnkey, supplying tied rebar, concrete, and form/finish.

  • Keppel AmFELS LLC

  • Contact: Octavio Gomez, 956-547-3324

  • Scope: (48) 30” X 55’ Straight Shafts; Provided turnkey services – supplied tied rebar, concrete, and form/finish

  • Completed: July 2015

Six Flags Over Texas – SkyScreamer

A drilled pier foundation designed for the world’s tallest swing carousel ride that required seven 54-inch diameter by 70' temporary cased rock holes.

  • Contractor: Hidalgo Industrial Services

  • Contact: Leroy Hidalgo, 817-625-8222

  • Scope: (7) 54” X 70’ Straight Shafts – rock drilling

IAH Terminal B

The foundations plan to be drilled for IAH's Terminal B by Spring 2025. Over 664 different piers have been drilled and slurried, having five drill rigs on site knocking the work out.

  • Contractor: Baker Concrete

  • Scope: 664 total piers: 18", 24", 36", 48"x depth: 30'-60'

Traverse Wind 245k Substation

  • Contractor:  Cajun Industries, LLC.

  • Contact:  Alex 225-754-0275

  • (102) 24” to 60” X 9’ to 20’ Straight Shafts

  • Completed:  April 2021

.

TAMU Engineering Education Complex

The specialized drill machine and crew completed 5-foot diameter belled piers by 12-foot deep with only 13’ of head clearance inside a basement. The second phase required a crawler crane with drill attachment to complete holes up to 9-foot diameter by 35-foot deep. Both phases were completed ahead of schedule.

  • Contractor: Vaughn Construction

  • Contact: Cody Matthews, 281-773-4414

  • Scope: (138) 18” X 108” to 96” X 192” Belled Shafts 20’ to 35’ in Depth

  • (2) 36” X 72” X 11’, (3) 54” X 108” X 12’, (4) 60” X 120” X 12’, (1) 66” X 132” X 12’ Belled Shafts

  • Completed: December 2015

FedEx Package Distribution Center

This addition to the distribution center was completed while accommodating the needs of an operational facility on a 101-acre site; construction was scheduled without disrupting ongoing operations. A crawler crane with drill attachment and Soilmec completed all temporary cased shafts ahead of schedule.

  • Contractor: Bean Concrete Construction

  • Contact: Kevin Mask, 469-742-0094

  • Scope: (173) 30” & 48” X 47’ Straight Shafts, 30” to 60” X 60” to 120” X 14’ Belled Shafts; Set and pulled casing for straight shafts

  • Completed: February 2014

Danbury Substation

  • Contractor:  Front Line Power Construction

  • Contact:  Jimmy 281-710-9155

  • (118) 18″to 84” X 15’ to 34’ Straight Shafts

  • Drilled and processed the 42″ & 84″ shafts by the slurry displacement method

  • Completed:  March 2022

.

M.D. Anderson Cancer Center

This project was for the M.D. Anderseon Cancer Center. Working 6 days a week drilling down to depths of 110' for 381 piers, this project was completed by December 2024.

  • Contractor: Baker Concrete

  • Scope: 381 total: 30", 42", 48"x depth: 35'-110'

BP Biofuels

  • Contractor:  Pinnacle Plant Services, Inc.

  • Contact:  Kris Miller, 409-622-1085

  • (6) 30” X 24’ to 37’ Straight Shafts

  • Processed by slurry displacement

.

Kyle Field Redevelopment Project

A $485 million redevelopment project that spanned over 2 years, involving over 1,500 drilled shafts that required temporary casing, low clearance areas, and an expedited schedule that included up to six drilling rigs onsite working seven days per week.

  • Contractor: Vaughn Construction – Manhattan/Vaughn

  • Contact: Cody Matthews, 281-773-4414

  • Scope: (970) 18” X 36” X 40’ to 66” X 186” X 60’ Belled Shafts

  • Scope: (619) 18” X 36” X 40’ to 66” X 156” X 60’ Belled Shafts; Supplied six rigs to meet schedule – finished one week before deadline

  • Completed: February 2015

HMSLH Bed Tower & Cath Lab

  • Contractor:  Vaughn Construction

  • Contact:  Todd Kast, 210-793-6059

  • (38) 30” X 65’ Straight Shafts

  • Processed by the slurry displacement method

  • Completed:  August, 2014

.

Hero Stadium

  • Contractor:  Sturdisteel

  • Contact:  Paul Medina, 423-261-4404

  • (124) 18”, 24” & 30” X 20’ to 36’ – rock drilling

  • Completed:  February, 2013

.

George R. Brown Convention Parking Garage

A 1,900 car parking garage located on the north side of the GRB. A constrained site, existing metro rail and downtown location were just a few obstacles encountered. Working alongside Vaughn Construction and Cemex Concrete, over 5,000 yards of grout were placed. Two auger cast drill machines and crews were mobilized to complete piles with a very demanding schedule.



  • Contractor: Vaughn Construction Company

  • Contact: Seth Hawes, 281-300-6855

  • Scope: (723) 18” X 100’ Auger Cast Piles; Drilled, supplied and placed grout, placed rebar cages

  • Completed: January 2015

bottom of page