Projects List
Texas A&M University-RELLIS Campus Industrial Distribution Center
Contractor: Jon Tucker Construction, Ltd.
Contact: Jon 979-412-1223
(94) 18” X 40’ Auger Cast Piles
Drilled, supplied and placed grout, grout pump & placed rebar cages
.
Kinder Morgan Galena Park Terminal
Cima Services selected Batten Drilling to complete Kinder Morgan Galena Park terminal bus support and
bridge foundations. Job was completed in 2 weeks; ahead of schedule and no change orders issued.
Over 500 yards of grout were placed.
Contractor: CIMA Services, LP
Contact: Collin Dodd, 832-690-0990
Scope: (64) 18” & 24” X 40’ to 60’ Auger Cast Piles; Drilled, supplied and placed grout, placed rebar cages
Completed: July 2015
Shell Gas Compression Facility
Contractor: Tepsco
Contact: Jim Wheeler, 281-542-2190
(396) 12”, 16”, 18”, 24”, and 30” X 8-21’ Straight Shafts
.
Keppel AmFels – Parker Drilling Foundation
Designed for Parker Drilling land rig. Forty-eight 30" by 55' deep foundations completed, being formed 2' out of ground. Batten Drilling provided all shafts turnkey, supplying tied rebar, concrete, and form/finish.
Keppel AmFELS LLC
Contact: Octavio Gomez, 956-547-3324
Scope: (48) 30” X 55’ Straight Shafts; Provided turnkey services – supplied tied rebar, concrete, and form/finish
Completed: July 2015
Six Flags Over Texas – SkyScreamer
A drilled pier foundation designed for the world’s tallest swing carousel ride that required seven 54-inch diameter by 70' temporary cased rock holes.
Contractor: Hidalgo Industrial Services
Contact: Leroy Hidalgo, 817-625-8222
Scope: (7) 54” X 70’ Straight Shafts – rock drilling
IAH Terminal B
The foundations plan to be drilled for IAH's Terminal B by Spring 2025. Over 664 different piers have been drilled and slurried, having five drill rigs on site knocking the work out.
Contractor: Baker Concrete
Scope: 664 total piers: 18", 24", 36", 48"x depth: 30'-60'
Traverse Wind 245k Substation
Contractor: Cajun Industries, LLC.
Contact: Alex 225-754-0275
(102) 24” to 60” X 9’ to 20’ Straight Shafts
Completed: April 2021
.
TAMU Engineering Education Complex
The specialized drill machine and crew completed 5-foot diameter belled piers by 12-foot deep with only 13’ of head clearance inside a basement. The second phase required a crawler crane with drill attachment to complete holes up to 9-foot diameter by 35-foot deep. Both phases were completed ahead of schedule.
Contractor: Vaughn Construction
Contact: Cody Matthews, 281-773-4414
Scope: (138) 18” X 108” to 96” X 192” Belled Shafts 20’ to 35’ in Depth
(2) 36” X 72” X 11’, (3) 54” X 108” X 12’, (4) 60” X 120” X 12’, (1) 66” X 132” X 12’ Belled Shafts
Completed: December 2015
FedEx Package Distribution Center
This addition to the distribution center was completed while accommodating the needs of an operational facility on a 101-acre site; construction was scheduled without disrupting ongoing operations. A crawler crane with drill attachment and Soilmec completed all temporary cased shafts ahead of schedule.
Contractor: Bean Concrete Construction
Contact: Kevin Mask, 469-742-0094
Scope: (173) 30” & 48” X 47’ Straight Shafts, 30” to 60” X 60” to 120” X 14’ Belled Shafts; Set and pulled casing for straight shafts
Completed: February 2014
Danbury Substation
Contractor: Front Line Power Construction
Contact: Jimmy 281-710-9155
(118) 18″to 84” X 15’ to 34’ Straight Shafts
Drilled and processed the 42″ & 84″ shafts by the slurry displacement method
Completed: March 2022
.
M.D. Anderson Cancer Center
This project was for the M.D. Anderseon Cancer Center. Working 6 days a week drilling down to depths of 110' for 381 piers, this project was completed by December 2024.
Contractor: Baker Concrete
Scope: 381 total: 30", 42", 48"x depth: 35'-110'
BP Biofuels
Contractor: Pinnacle Plant Services, Inc.
Contact: Kris Miller, 409-622-1085
(6) 30” X 24’ to 37’ Straight Shafts
Processed by slurry displacement
.
Kyle Field Redevelopment Project
A $485 million redevelopment project that spanned over 2 years, involving over 1,500 drilled shafts that required temporary casing, low clearance areas, and an expedited schedule that included up to six drilling rigs onsite working seven days per week.
Contractor: Vaughn Construction – Manhattan/Vaughn
Contact: Cody Matthews, 281-773-4414
Scope: (970) 18” X 36” X 40’ to 66” X 186” X 60’ Belled Shafts
Scope: (619) 18” X 36” X 40’ to 66” X 156” X 60’ Belled Shafts; Supplied six rigs to meet schedule – finished one week before deadline
Completed: February 2015
HMSLH Bed Tower & Cath Lab
Contractor: Vaughn Construction
Contact: Todd Kast, 210-793-6059
(38) 30” X 65’ Straight Shafts
Processed by the slurry displacement method
Completed: August, 2014
.
Hero Stadium
Contractor: Sturdisteel
Contact: Paul Medina, 423-261-4404
(124) 18”, 24” & 30” X 20’ to 36’ – rock drilling
Completed: February, 2013
.
George R. Brown Convention Parking Garage
A 1,900 car parking garage located on the north side of the GRB. A constrained site, existing metro rail and downtown location were just a few obstacles encountered. Working alongside Vaughn Construction and Cemex Concrete, over 5,000 yards of grout were placed. Two auger cast drill machines and crews were mobilized to complete piles with a very demanding schedule.
Contractor: Vaughn Construction Company
Contact: Seth Hawes, 281-300-6855
Scope: (723) 18” X 100’ Auger Cast Piles; Drilled, supplied and placed grout, placed rebar cages
Completed: January 2015